AMI Grid Modernization Make Ready Design

Project Name:

AMI Grid Modernization Make Ready Design

Client:

A Fortune 500 integrated energy company in the southern United States

Project location:

Louisiana, Mississippi, Arkansas and Texas

Project Scope:

AMI Communications Network make-ready design

Challenge:

The client wanted to install automated smart meters across its service area and needed to ensure that the AMI Communications Network was designed to be installed on distribution poles in accordance with internal standards and applicable NESC codes.

Solution

The energy company turned to ULCS to provide a design support team with knowledge of its system, NESC standards and constructability.

Outcomes/Status:

ULCS exceeded expectations, designing the AMI Communications Network make-ready modifications to the distribution system according to code and with on-time deliverables.

Project Gallery

Project Services